How long does it take to build?




This report offer an order of magnitude of the time required for the management of the order in standard working conditions.




This timetable is purely indicative and reports an order of magnitude of the time required for the management of the order in standard working conditions.

The drafting of the Feasibility Study will require from one month to four months

The due diligence usually lasts up two months. If the due diligence is passed, the Funds will begin disbursing after approximately 6 months (the months of August and the Christmas period must not be considered). 

Engineering usually takes from 3 to up to 6 months.

The construction of any device will begin after the completion of the detail design.

Normally, the costruction of our devices require from 6 months to a year from detail design acceptance.

Transport, installation, commissioning until archiving of the expected performance levels takes from 2 to 6 months, excluding customs clearance times.

Therefore, from receiving the money from the Costumer or by the Fund, we will take approximately from 14 to 36 months to produce, deliver and install any device, as well as the imponderable customs clearance times.

As the size of the project grows, the construction time will increase.

 production

7 days +/-
Contract verification and signature
120 days (up to)
Drafting of the project - feasibility study
60 days (up to)
Fund due diligence
90 days +/-
Engineering
180 days (up to)
Construction
60 days (up to)
Factory assembly
14 days +/-
Pre-Testing and ready to ship
180 days (up to)
Testing and commisioning