How long does it take to build?




This report offer an order of magnitude of the time required for the management of the order in standard working conditions.




This timetable is purely indicative and reports an order of magnitude of the time required for the management of the order in standard working conditions.

The drafting of the Feasibility Study will require from one month to four months

The due diligence usually lasts up two months. If the due diligence is passed, the Funds will begin disbursing after approximately 6 months (the months of August and the Christmas period must not be considered). 

Engineering usually takes from 3 to up to 6 months.

The construction of any device will begin after the completion of the detail design.

Normally, the costruction of our devices require from 6 months to a year from detail design acceptance.

Transport, installation, commissioning until archiving of the expected performance levels takes from 2 to 6 months, excluding customs clearance times.

Therefore, from receiving the money from the Costumer or by the Fund, we will take approximately from 14 to 36 months to produce, deliver and install any device, as well as the imponderable customs clearance times.

As the size of the project grows, the construction time will increase.

 production

7 days +/-
Contract verification and signature
120 days (up to)
Drafting of the project - feasibility study
60 days (up to)
Fund due diligence
90 days +/-
Engineering
180 days (up to)
Construction
60 days (up to)
Factory assembly
14 days +/-
Pre-Testing and ready to ship
180 days (up to)
Testing and commisioning

CE ECO EN

We are including articles, graphics and brochures on the site that can also be downloaded in French, Italian, Spanish and Portuguese.

During insertion, some pages will be temporarily unreachable.

We apologize for the inconvenience.

CE ECO FR

Nous sommes en train d'insérer sur le site des articles, des graphiques et des brochures qui peuvent également être téléchargés en français, italien, espagnol et portugais.

Lors de l'insertion, certaines pages seront temporairement inaccessibles.

Nous nous excusons pour le dérangement.

CE ECO IT

Stiamo inserendo nel sito gli articoli, le grafiche ed i depliant scaricabili anche in francese, italiano, spagnolo e portoghese.

Durante l'inserimento alcune pagine saranno temporaneamente non raggiungibili.

Ci scusiamo per il disagio.

CE ECO PT

Estamos em processo de inserção de artigos, gráficos e brochuras no site que também podem ser baixados em francês, italiano, espanhol e português.

Durante a inserção, algumas páginas ficarão temporariamente inacessíveis.

Pedimos desculpas pela inconveniência.

CE ECO ES

Estamos en proceso de inserción de artículos, gráficos y folletos en el sitio que también se pueden descargar en francés, italiano, español y portugués.

Durante la inserción, algunas páginas serán temporalmente inaccesibles.

Nos disculpamos por el inconveniente.